Tuesday, July 24, 2012

Tuesday 24th July

The boys are back this morning, Bricks are being cleaned, skirting boards, windows, doors etc to be done today and tomorrow.
Painting is starting next week.


Laundry - Washer and Dryer will sit under bench either side of the cupboards.
More Cupboards to be installed above after we move in!


Kitchen - Stone Benchtop to be installed last with Dishwasher


Kitchen - Oven will be installed last with Rangehood.


Kids Bathroom - bath won't be installed till last


BiFolds


Master Ensuite - we are also having a cupboard from ceiling to floor installed either side of the vanity.  There will be a full size mirror here too!

Thursday, July 12, 2012

Thursday 12 July


Front door entrance


Laundry


Theatre


Study


Master Bedroom


Kitchen, Living & Dining (Far left)


Walk in Pantry & Dining area


Bathroom


Rumpus Room


Kids Bedroom


Hallway

Wednesday, July 11, 2012

Wednesday 11th July

WALL INSULATION IS DONE..............


Front Door


Bifolds leading out to Alfesco


Master Ensuite


Kids Bedroom

Friday, July 6, 2012

Friday 6th July


Kids Bathroom


Rumpus Sliding Door & Living Room Window


Study Windows


Alfresco - Total mud pit at the moment


Garage

Wednesday, July 4, 2012

Wednesday 4th July


Roof is all completed, Gutter & Fascia all done.



This is the Garage Wall


Left side of house, boys were back at 7.30am this morning!